Liwan 3-1 3rd Party Verification: Jacket Design and Float-Over Installation
• Timeline: 2010
• Location: South China Sea
• Water Depth: 200m
• Operator: CNOOC
• Client: COOEC
Project Description:
Liwan 3-1 is China’s first deepwater project with an estimated contingent reserves of between 4 trillion and 6 trillion cubic feet of gas. While the deepwater depths approach 1500m, the Central Processing Facility sits in 200m depth and is connected to the field via a 100km subsea pipeline. It is estimated that the jacket is the largest single piece jacket.
ODL Scope of Work:
ODL was contracted to complete a 3rd party verification of the basic design of the Liwan 3-1 jacket and to design the float-over installation of the Central Processing Facility.
Key Details: