Liwan 3-1 3rd Party Verification
BaJiaoTing Field: Jacket and Deck Design
PanYu 30-1 New Jacket Analysis and Design
Pontoon Barge Float–Over Installation Study
North Belut CPP Platform
Float – Over Installation Engineering Services
Pontoon Barge Float–Over Installation of BZ28–2S Field
Vyborg SSFDR Topside Float-over
FRICTION Fender Floatover Study
Talisman MOPU Stor Dry Installation
Castor WHP Jacket floatation and upending analysis
Chevron Concept selection Study
CNOOC shallow water Mooring Design Study
Project Description:
The North Belut field is located in Block B of the Indonesian sector of the Natuna Sea.ODL was contracted from ConocoPhillips Indonesia to perform CPP Platform float over installation engineering services. The CPP platform weights 14,000 tons.
ODL Scope of Work:
ODL performed the float over installation engineering services.
Key Details:
Review and 3rd party verify all the installation procedures documents from the main contractor
Perform float over installation engineering analysis ( includes stand off; entry; mating; exit stage) based on the input from contractor.