Project Description:
Ocean Dynamics LLC/Offshore Kinematics Inc. was awarded the float-over installation scope for the WHP platform of the Corocoro Field located in the Gulf of Paria in Venezuela.
ODL/OKI Scope of Work:
ODL performed the ‘virtual installation’ as the 'virtual' General Contractor. The Scope included the configuration design and detailed engineering of the T&I of the WHP, assistance with the procurement of all equipment and resources, the proposal detailing the modification of the deck and the jacket during the float-over installation, inspection and modification of the installation barges and offshore installation supervision.
Key Details:
The float-over operation only took about 2 hours from the start of the operation to the mating of the deck legs with the jacket topside.